Featured Case Study

Lady Bird Johnson Middle School in Texas utilizes GeoHC to Cut Energy Use

Featured Image
The First Net Zero Public School in Texas and the largest in the US

Located in the Dallas-Fort Worth Texas area and completed in 2011, The Lady Bird Johnson Middle School was built to produce as much energy as it consumes. In addition to 3,000 solar panels and 23 wind turbines generating electricity on campus, the school implemented a daylighting design and unique metal-clad canopy that tracks the sun’s trajectory to maximizes natural light in each classroom while shading against the worst of the hot Texas sun. The school also incorporates a rainwater collection system to reduce municipal water demand.

The building utilizes geothermal heating and cooling (GeoHC) to keep the temperatures comfortable all year long while dramatically reducing energy consumption compared to traditional HVAC units in the hot Texas climate. As a result, the building uses 2/3 less electricity than other schools in the district.

The building itself serves as a teaching tool for the students and guests, with museum-quality interactive displays depicting real-time data on the school’s cutting-edge conservation technology. Learning centers throughout the school teach students how these technologies work, including a Geothermal Science Learning Center.

Key Findings

  • Geothermal Heating & Cooling (GeoHC) provides the heating and cooling for the school, generating 590 tons of air conditioning
  • 105 geothermal heat pumps account for 30% of the overall energy-reduction strategy.
  • The school was awarded a LEED Gold Certification

Key Metrics

  • 152,250 square foot campus serves 900 students in the sixth through eighth grades
  • 107 Bosch FHP model EV and EC geothermal water source heat pumps from 1 to 20 tons
  • 505 geothermal wells bored approximately 250 ft deep
  • Cost approx. $30 million to build the entire school, completed in 2011
  • $3.75 million of the $30 million was spent on the energy efficient design strategies and technologies

Lessons Learned

[mission_geo_lessons_learned]
  • The district was committed to investing in these technologies and understood that the short-term construction costs would provide long-term operational savings.
  • Monitoring and display systems were incorporated to track performance and identify maintenance needs.
  • The technologies used to fuel the building were incorporated into the curriculum, turning the building into a teaching tool for students and those wishing to study its benefits